jyoticlub Posted April 11, 2006 Posted April 11, 2006 21 men were employed to do a work in a cetain time.When 1/3rd of the time was completed only a quarter of work was done.How many more men should be employed to complete the work in 3/4th of the scheduled time. I got the answer as 11.(i am not sure)Can u help!! Jyoti
5614 Posted April 11, 2006 Posted April 11, 2006 You can tell that is wrong just by looking at. They have done 25% of the work in 33% of the time, clearly they need more people. And 11 is less. I wouldn't say I know how to do it because I don't, but here is my method of thinking: Say it takes 3hrs to do all of the work (just because we are dealing with 3rds) so when 1/3 of the time is gone that is 1hr of work for each of the 21 men. If 21 people do 1 hour of work we have 21hours of work in total. If 21hrs of work = 25% then 75% = 21*3 = 63 hours of work. If we have 2/3 of the time then we have 2 hours. And we need 63hrs of work done in 2. So we need 63/2 men, which is 31.5 men, which we must round to 32 men. Let's try putting that more mathematically: Assume total working time for all men is 3 hours. So 1/3 time = 1 hour [math]21men \times 1hr = \frac{1}{4} work = 21[/math] So 2/3 of the time is 2 hours [math]Number Of Men \times 2hrs = \frac{3}{4} work = \frac{1}{4} work \times 3 = 21 \times 3 = 63[/math] [math]No. Men \times 2hrs = 63[/math] [math]No. Men = \frac{63}{2hrs} = 31.5 \to 32[/math]
Dave Posted April 11, 2006 Posted April 11, 2006 Well, you just confirmed his answer; the question states "how many more men", not "how many men" Your answer of 32 corroborates his of an 11-man increase.
5614 Posted April 11, 2006 Posted April 11, 2006 Ah, yeah, good point... wrote down the data on some paper and worked it out, then forgot to actually read the question ... yeah, 11 more sounds good. Ah well, it was a nice question to do.
abskebabs Posted May 19, 2006 Posted May 19, 2006 Eek! I got a different answer to you guys when doing this(you may notice I'm a complete amateur with latex, this took me way too long). I first worked out a rate the men would be working at by dividing the work done by the time. Then I divided this by the number of ppl to give me the rate per person. I thne worked out the rate that would be required to finish the work with a quarter of the time to spare. I had to first find the remaining time by taking away a third from 3 quarters. Finally I divided the required rate by the rate per person to give me a number. [math]rate= \frac{\frac{1w}4}{\frac{t}3}= \frac{3w}{4t}[/math] [math]rate/person= \frac{\frac{3w}4t}{21p}= \frac{w}{28tp}[/math] [math]time.remaining=\frac{3t}{4}-\frac{t}{3}= \frac{5t}{12}[/math] [math]requiredrate=\frac{\frac{3w}4}{5t/12}= \frac{9w}{5t}[/math] Therefore to find the number of ppl needed after a third of the time has passed: [math]No.people=\frac{9w/5t}{w/28tp}= \frac{252p}{5}= 50.4[/math] Therefore the total number of ppl required to do the job in time after a third of the time has passed within 3 quarters of the time has to be at least 51. You would therefore need 30 more ppl. I'm not sure if this is correct...
5614 Posted May 27, 2006 Posted May 27, 2006 I can't find a specific mistake in your calculations. I don't know if you can just use w, p & t as variables like that. All I can really say is that you are using the wrong method and the wrong way of thinking about/approaching the problem. You've got the correct way (incl. solution) above so use that. Sorry I can't help more.
abskebabs Posted May 27, 2006 Posted May 27, 2006 I think I see the difference in our methods. I assumed that the work had to be done within 3 quarters of the total time after a third of the time had passed. It doesn't seem to me you took into account that the work needed to be completed within 3 quarters of the time, I think. I'm not sure:confused: ? Where's a maths moderator when you need one:rolleyes: .
Dak Posted May 27, 2006 Posted May 27, 2006 none of your fancy squiggles and symbols for me... it's brute-forsing with basic maths all the way 21 people = 25% of total work (in 33% of total time) {divide by 21} 1 person = 1.19% of total work (in 33% of total time) or (1 person) 1.19% of total work = 33% of total time {divvy by 33} (1 person) = 0.036% of total work = 1% of total time. Now, they've used 33% of the time and need to complete the work 25% ahead of scedule, so they have 100% - 33% - 25% = 42% of the total time left. {times by 42%} (1 person) 1.51% of total work = 42% of total time {or} 1 person = 1.51% of total work (in 42% of total time) Now, they have 75% of the work outstanding, so times by 75/1.51 rounded up {times 50} 50 people = 75.5% of total work (in 42% of total time). which is enough to get the remaining work done in the time remaining. and as they have 21 people, they need 50 - 21 = 29 more people. Which, give-or-take for my rounding, is abskebabs' answre. in summary: abskebabs was right, 5614 needs to read questions more carefully , and i still don't think all those funny squggles that you guys use are neccesary
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now